Astana's LRT: First Carriages Arrive, Launch Expected by Early 2026
Astana's LRT System: On Track for Completion. Astana, Kazakhstan – The first carriages of Astana's much-anticipated LRT system have arrived, marking a significant step towards the completion of the project. Astana Mayor Zhenis Kasymbek, speaking to reporters on June 9th, 2025, confirmed that all trains are expected by the end of summer. "By the end of the summer, all the trains will be here. We plan to start technical testing in September," he stated. Following this, Kasymbek indicated that the project anticipates three to six months of testing before full passenger service commences, likely by the end of the first quarter of 2026. The arrival of these carriages signals a major step forward for Astana's public transportation infrastructure, promising improved efficiency and convenience for residents.